operation details- base quantity

Hi, my operation base qty is 100, order qty is 1000, total hours required (setup+machine) is 10 hrs. this info is from production order operation detail. here please advise how to calculate the total duration to complete the order? is the hours specified (setup+machine) for base qty? please advise.

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • May 15 at 07:21 AM

    Thanks Almedia, using the formula in scheduling view of cr03- i got 100 hrs. so this 100 hrs will be scheduled from current date (say i have created order today) from 15.05.18, 00:00:00 to 18.05.18 04:00:00, considering each day as 24 hrs? is it correct? or if my work center available capacity is only 9 hrs, i this case will it schedule considering each day as 9 hrs span. please clarify.

    Add comment
    10|10000 characters needed characters exceeded

  • May 14 at 05:28 PM

    Hello

    Total operation duration will depend on the formula defined in the work center.

    Go to transaction CR02 and on tab scheduling you will find an option to test the formula, where you can input all the parameters and see the results.

    Regards,

    Caetano