operations scheduling

May 14 at 02:05 PM

23

avatar image

Dear experts, capacity of my work center is 9 hrs per day as per capacity view of the cr03. now i created a production order with that work center in operations. i need total of 36 hours (setup+processing) to complete this order. so please advise how this operation will be scheduled, will system consider 9 hrs per day and accordingly it will schedule for 4 days? is my understanding correct?

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

1 Answer

Jessica Li
May 15 at 12:41 AM
0

Hi Raju,

Scheduling is based on the formula and standard values of routing. Formula are set in Scheduling and Capacity tab in Work center, standard values are set in routing and can be adjusted in order. Details you can see note 150007 - Consulting: Scheduling of production orders.

Also KBA 2584494 - Scheduling in Process Order contains detailed calculation logic, but it is for process order. Hope the point 2,3,4,5 in solution part can give you some idea how formula is calculating.

BR,

Jessica