operations scheduling

99 Views

Dear experts, capacity of my work center is 9 hrs per day as per capacity view of the cr03. now i created a production order with that work center in operations. i need total of 36 hours (setup+processing) to complete this order. so please advise how this operation will be scheduled, will system consider 9 hrs per day and accordingly it will schedule for 4 days? is my understanding correct?