Dear PPs,

I input Min. Overlap time 60 Min in routing with "required overlapping", there are three operation as following, just ignore wait, queue and move time. Processing time is 60 min/pc in each operation. I create a production order with qty 3 PC.

The order schedules as below:

Start End

0010 19:00 22:00

0020 19:00 22:00

0030 19:00 22:00

I just doubt why there are the same scheduling for each operations, and no overlapping function by using field"Min. Overlap time ", and i do successfully with field "Min. send-ahead qty", can anybody tell me about this?

Thanks.