Hi All,

We are going to upgrade support package from SP11 to SP17. could you please help what will be pre and post checks to be performed in high level.

is there any impact on PI interfaces with this upgrade?

Regards,

Janardhan

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

1 Answer

Tom Xing
May 16 at 02:07 AM
0

Hi Janardhan,

Before upgrade, I suggest you close all changelists in ESR and Integration Builder.

After upgrade, make sure you

- run CTC wizard according to note 1444305 - Configuration Wizard: PI / ESR Support Package Update

- test all interfaces

Generally we don't expect any impact during SP upgrade.
However it may still happen.

Best regards,
Tom