on 11-24-2008 9:53 AM
Hi All,
If I activate avl check at Order Level and I create a SO for a BOM Material--the avl check will carry out for the component materials as well right?
Regards,
Raghu.
unans.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear Ragu,
If you maintain the availability check related settings in the components master data then system check the availability for components also at sales order level.
I hope this will help you,
Regards,
Murali.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.