Hi PP Experts.

Is it possible to take goods movement in TECO process order directly.

is there any other possibility for take goods movements in TECO process order?

Accepted Solutions (1)

Accepted Solutions (1)

rupesh_brahmankar3
Active Contributor
0 Kudos

Dear,

Yes it possible to take goods movement after TECO process order.

If you want to restrict it then,

then go to BS22 (Maintain System Statuses) you can handle the Situation..

Travel to I0045 - TECO- Double Click on that.

Select the Business Transaction RMRU (Confirm order) - It will be in Permitted Ststus.

So, Change that to Forbidd.

Regards,

R.Brahmankar

Answers (3)

Answers (3)

Former Member
0 Kudos

In this case we can give authorization to Finance department to revoke TECO of production order.

Former Member
0 Kudos

Yeah. Just like the answers all of above. Generally, when the production department has finished the production orders or process orders, and they don't want to change them any more, so they use the status TECO to close the orders. therefore, goods movement is forbidden. But finance department can deal with them.

Former Member
0 Kudos

Hi,

After TECO you can't do Goods Movements. For carrying out , GOOds Movements you need to revoke TECO in process order as following :

GO to COR2-> Process Order Menu->Functions->Restrict Processing-->Revoke Technical Completion and Save.

After revoking TECO , You can carry out Goods Movements.

Hope this helps.

Revert if any doubt.

Award points if useful.

Regards,

Tejas

Former Member
0 Kudos

this right way.

thanks

but problem is all material which are allocated to order. is create a new TR for materials and re reservations.