Former Member
Nov 23, 2008 at 08:36 PM

capacity and production order

727 Views

Hi,

After creation of production order thru MRP run, if I find my work centres involved in routing to be overloaded what needs to be done. I am referring to capacity levelling. If i find my work centres red in color in cm01, what suggestions should i give to my client?

my client says he wants to schedule in a later date whenever the work centres are next available, how to do this?

Say prodcution order is of 10 quantity.my client says if it is over loaded, he wants to do some number of quantity in house production and rest he would get it from vendor. but how to decide how much to do in house so that work centre is 100 % loaded or else 90% and what quantity to send it to vendor?

as I understand , after production order is created, i can see the work load in CM01. ( what is the actual procedure, please tell me) if it is non red i will release it, if it is red, what to do??

Please help.

Regards.