Dear all,

I have 2 storage locations, connected to the same warehouse number.
When I create an sloc2sloc transfer posting with MvT 311, the system (by standard) creates a posting change notice. If I use a 2-step process with MvT 313 & 315, I get two Transfer requirements.


Moving parts between those storage locations includes a physical movement, so I would like to use a process in which:

- the source bin is determined automatically

- the destination bin is determined based on storage location reference

- the TO creation in WM can be triggered automatically in the background.

- stock removal and -placement should be triggered by one step in IM.

My Problem:

1. I can't process TO for PCN in the background: Standard PCN-Behaviour requires the user to choose the correct quant if the material is spread across several bins/storage types --> To creation fails if set to "A" - Automatic creation in background.

2. The 2-Step process works without PCN, but I need it as a 1-Step process.

Is it possible to just deactivate the PCN creation for MvT 311 (by replacing the transfer posting wm reference by 999) or are there any downsides to that?

Regards,

Lukas

Add comment
10|10000 characters needed characters exceeded

  • Former Member

    Additional Comment:

    Expectation would be to be able to trigger two TR, one for picking (from source sloc), one for putaway (in destination sloc, with bin determination according to sloc reference)