Hi,

for an article we have fixed planned orders.

Although the quantities of these orders covers the total demand, the MRP still creates additonal planned orders whenever a certain demand can not be fullfilled at the required date.

We do not want this, the stock in MD04 should go negative since planned orders - that are for the moment later planned then the demand is - covers everything.

How can this be achieved please?

Many thanks in advance!!!

danny

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • May 15 at 09:17 AM

    Danny,

    Have you considered rescheduling horizons?

    https://wiki.scn.sap.com/wiki/display/ERPMan/What+is+rescheduling+and+how+does+it+work

    Rajen