MRP creates unneeded planned orders

May 15 at 08:17 AM

20

avatar image

Hi,

for an article we have fixed planned orders.

Although the quantities of these orders covers the total demand, the MRP still creates additonal planned orders whenever a certain demand can not be fullfilled at the required date.

We do not want this, the stock in MD04 should go negative since planned orders - that are for the moment later planned then the demand is - covers everything.

How can this be achieved please?

Many thanks in advance!!!

danny

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

1 Answer

Rajen Madan May 15 at 09:17 AM
1

Danny,

Have you considered rescheduling horizons?

https://wiki.scn.sap.com/wiki/display/ERPMan/What+is+rescheduling+and+how+does+it+work

Rajen