I have an issue when running Production lot costing CKW1. The BOM has a Routing with several operations, one of which is referring to an external processing Operation. There is a Purchase Info record set up for this, with an info category - Standard. When CKW1 is run for one of the materials specified, an error is generated:
MsgNo 467 No price could be determined for external processing
Consequently a new PIR was created that was linked to an info category - sub contracting. The routing operation relevant to the material was changed, i.e. in the external processing view, the PIR no. was changed from the standard info cat. to the sub. contract info category and the subcontracting indicator ticked.
When CKW1 was then run the costing was successful
I can not work out why the costing is failing with a standard PIR but works with a subcontracting PIR?
The Production lot costing variant has a valuation variant -->
external processing --> strategy sequence --> 1 Price from Operation
2 Net quotation price
Edited by: neil Marsh on Nov 23, 2008 4:30 PM