Hi SAP,

I try to do a GR for a scheduling agreement via MIGO the system gives me an error message saying that "Scheduling agreement xxxxx does not contain any selectable items" .

Does anyone know what this error is and how can I take care of it ?

Rgds

Karan

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi john,

1. Have you released the schedule lines?

2. Check for dates also GR date should not earlier/later than aggrement date.

3. Check for GR qty, if it is completly delivered?

hope it will help..

Cheers..........

manoj

Answers (5)

Answers (5)

Former Member
0 Kudos

Hi

Please check the below thread.

Regards

Prasad

Former Member
0 Kudos

Dear Friend,

It could be because of one of the following reasons.

1.Schedules lines were not created.

2. Scheduling agreement does contain confirmation code for eg ASN, Confirmations. It should be with "Rough GR"

Please check for these two points and let me know.

Ganesh

Former Member
0 Kudos

maintain Sche. Aggmt by ME38

Former Member
0 Kudos

Dear,

Pl release Document to all the levels..

or pl check whether already GRN exist..

former_member225662
Active Contributor
0 Kudos

Hi,

Have you released the schedule lines?

Check for dates also GR date should not earlier than aggrement date.

Regards

KK