Want to Lock My closed Project

ansar_shaikh2
Contributor
0 Kudos

Hi PS MAsters!

One of my client need to lock the Project after closing the Project.

that means, After complete closing the Project, no one can view the Project except Person Responsible.

Is it possible ..please let me know how to do it

Thnx & Regards,

ANSAR

Accepted Solutions (0)

Answers (2)

Answers (2)

ansar_shaikh2
Contributor
0 Kudos

thanx for ur input

virendra_pal
Active Contributor
0 Kudos

this is not available as standard functionality

you will need to develop using exit CNEX002

ansar_shaikh2
Contributor
0 Kudos

Sir can we use User Status...need to know whether it is possible..

Once the system status is Closed, no one can view the Project except Authorized people.

Regards,

ANSAR

virendra_pal
Active Contributor
0 Kudos

once you close the project the project system staus will be the governing criteria

use exit toi develop with functionality

when status CLSD then auth object for PRSP-VERNR display only, else error - not authorised to view project