Hi,

Here is my scenario.

We are working for process industries,where in we are not having MRP planning ,

So client wants to trace the Scrap ,post confirmation using MCP5(report).

Say for example:

If i created a process order for 100 ea,and want to confirm the scrap say 10 ea with cor6n,with final confirmation of only 90 ea(100-10).

Note :when i tried using Cor6n,system dint allow to enter the scrap for the phase confirmation..

i even tried maintaining the component scrap ,but of no use..