Dear SAP Experts,

Please tell me the various differences between MD01 and MD02.

In which specific cases, MD01 should be used??

Thanks and regards,

Kaushik Basu.

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

1. Md01 is the MRP Run for plant by giving planning scope.

2. Md02 is the mrp run for single Material from plant .

Also refer following T code for your information

Menu Nodes

Transaction

Activity

Master Data

MD25

Create planning calendar

MD26

Change planning calendar

MD27

Display planning calendar

MDSA

Display BOM explosion number

MDSP

Edit BOM explosion number

MEQ1

Maintain quota file

OPPP

Explode BOM by date

MDUS

Display project assignment

MDUP

Process project assignment

MDL1

Create production lot

MDL2

Change production lot

MDL3

Display production lot

Planning

MD20

Create planning file entry

MD21

Display planning file entry

MDAB

Set up planning file entry in background

MDRE

Check planning file entry

MD01

Total planning online

MDBT

Total planning in background

MD03

Single-item, single-level planning

MD02

Single-item, multi-level planning

MD43

Interactive single-item planning

MD50

Multi-level, make-to-order planning

MD51

Multi-level project planning

MF52

Display planning table

MF50

Change planning table

MF57

Planning table by MRP lists

MF51

Planning table by production list

Evaluations

MD04

Stock/requirements list

MD07

Collective access of stock/requirements lists

MD05

MRP list

MD06

Collective access of MRP lists

MDLD

Print MRP list

MD45

Planning result

MD46

Collective access of planning result

MD44

Planning situation for a material

MD47

Planning situation for a product group

MD48

Cross-plant planning situation

MD4C

Order report

MD09

Pegged requirements

CO46

Order progress

Planned Order

MD11

Create planned order

MD12

Change planned order

MD13

Individual access of planned order

MD16

Collective access of planned orders

MD14

Individual conversion of planned order into purchase requisition

MD15

Collective conversion of planned orders into purchase requisitions

MDUM

Convert planned order into purchase requisition in background

CO40

Convert individual planned order into production order

CO41

Collective conversion of planned orders into production orders

CO48

Partial conversion of planned order into production order

COR7

Individual conversion of planned order into process order

COR7_PC

Collective conversion of planned orders into process orders

COR8

Partial conversion of planned order into process order

MDVP

Collective availability check

MDAC

Execute action for planned order

Hope it clear to u.

Edited by: Atul Zod on Nov 21, 2008 6:59 AM

Answers (6)

Answers (6)

Former Member
0 Kudos

Dear Friend,

MD01 is used for All material planning in the perticular plant or for the group of plants maintianed under scope of planning. in this system will check stock and requirement of all materials and will do the planning.

MD02 is used only to plan single material in single plant. it will not check other material stock and requirement in the plant

sree

dhaval_choksi3
Active Contributor
0 Kudos

Hi ,

MD01 - Is a Total Planning Run.Using this Code you can run MRP for all plant specific materials.

or by using User Exit you can run MRP for particular MRP controller also.

MD02 - Is Used for Planing at Single Item Multilevel.In other words you can select only one Material at Header Level and system will plan up to the last level of BOM.

Regards,

Dhaval

Former Member
0 Kudos

Hi Dear,

MD01- it is used to run mrp for whole plant level without cosidering any material.

MD02- it is used to run mrp for material level which contains multilevel BOM. And also use it for perticular mrp areas also.

MD03- it is used to run mrp for material level which contains single level BOM.

Hope clear to you some extenct.

Regards,

Imran

rupesh_brahmankar3
Active Contributor
0 Kudos

Dear,

MD01- total planning run so here we run MRp for all plant or MRP Area,

So if client want to run MRp for all plant and materail in that case we use MD01

MD02-- For single materail at plant level.

Hope clear to you.

Regards,

R.Brahmankar

Former Member
0 Kudos

Hi ,

MD01 is for whole plant . For example you have done changes to most of the master data and you now want to see the MRP result . In this case you cant go for MD02 for each and every mat so you will use MD01.

MD02 - just for one mat , single item , multi level ( will explode whole BOM for particular mat )

Neal

Former Member
0 Kudos

MD01 is used to run MRP at plant level.

MD02 is used to run MRP for a particular Material

former_member207022
Active Contributor
0 Kudos

Dear

MD01 is used for running the MRP for speicific plant or number of plants to maintain the scope of planning. In the scope of planning you can maintain number of plants and can use the scope to run MRP for maintained plants.

MD02 is used for MRP run for specific finished product with a plant.