hi,experts,

here is my problem , sometimes ,the standard BOM has been changed ,for example ,add a new material to the BOM,but the BOM of some production order hasn't been changed ,so ,how to find out the production orders which include the new material ?

thanks

Jarod

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

We can get the report in COOIS.

Answers (2)

Answers (2)

Former Member
0 Kudos

Dear Jarod ,

If you have changed BOM after creating production order then it will not reflect automatically . First go to change prod order and check BOM components in comp overview and check if it is there otherwise from functions > Read PP master data .

For finding out prod orders which has'nt change you have to do some ABAP development .

Neal

rupesh_brahmankar3
Active Contributor
0 Kudos

Dear,

If you use the ECM- Engineering change management then it is possible to track the changes in BOm and Production order with OCM will given the component history.

Other wise you have to check in Production order Component over view you will get details of component.

Or you can check in USE table RESB with RSNUM of AUFK-AUFNR

or From CAUFV table u can get the material Number and the Plant for the coresponding PO number. and u can pass these Mat.no, Plant and BOM usage as '1'.

or go to these FMs:

1. CO_DB_HEADER_READ

2. CO_SF_AFPO_READ

Hope this will helpful.

Regards,

R.Brahmankar