on 11-20-2008 8:12 PM
Hi All Sap Guru,
I face one the problem in Quality server when i run the program APP through F110 the system is not updated check lot. Same exercise i tested in Development server then system updated check lot. I have checked the configuration FBZP and house bank. System is updated house bank in Development server but when we transport this request to quality server then system is not updated.
Can any one have solution this problem ::::::
Waiting your promot reply
Thanks in advance.
Regards,
Pankaj
Make sure check lots are created in Quality server.
Also make sure that in F110 you perfomr the Print function after the payment run update. The check numbers are updated only during the print function.
Regards,
~Vishal.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Thanks for your reply but i have checked the check lot are created and also maintain new variant.
System again not updated check lot.
When i check the house bank both side Development and Quality server then system is now showing Bank IN Key 001 does not exist.
Please help in this situation.
Regards,
Pankaj
User | Count |
---|---|
94 | |
11 | |
10 | |
6 | |
5 | |
5 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.