Hey folks

Many thanks for your helpful suggestion but i have another question.

We currently run a background job that checks our Maintenance plans and create work orders for Preventive maintenance work that are due.

The log file generated at the end of the background job presents the error as belo:

''You must specify a batch for material 42110023''

It does not make reference to any specific work order or maintenance plan which could have been really helpful in terms of reconciliation and resolution of issues.

Do you have any thought on how this could be implemented/ fixed?

Thanks for your help.