Employees use CATS to record their working hours. Within the week, everything works just fine.
On weekends they use a daily work schedule with "No planned working hours" crossed (same work break schedule as within the week). Due to this (my assumption), the dynamic breaks don´t work (they are not taken into account). In T550P, entries are as follows:
01 Schedule 01 0,50 0,00 6,00 N
01 Schedule 02 0,25 0,00 9,51 N
How can I make this work or what am I doing wrong?
Thanks in advance.
Hi,
When we use Variant DWS and Flexi DWS we do not use Break Schedule.
Breaks can specify any number of breaks within the employee's planned working time, and a maximum of four overtime breaks (outwith the planned working time). Only in the planned working time.
Warm Regards
Kapil Kaushal
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
89 | |
7 | |
6 | |
3 | |
3 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.