hi all,

how to create the production order directly from run the mrp . without the planned order creation.

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

Hi,

You have give requirements in MD81.

And then execute a planning run .

Reg,

Deepak.

Edited by: deepak k b on Nov 20, 2008 9:55 AM

Former Member
0 Kudos

if i get the sales oder. after run the mrp . it should directly generate the production order.

instead of first create the plnn order and convet in to the prod order

how and where we have to do the setting

did any std config is there or not?

former_member225662
Active Contributor
0 Kudos

HI,

Check T code OMDV and maintain the settings there from Planned order to Production order.

Regards

KK

Former Member
0 Kudos

Hi,

Use strategy type 82(Assembly orders with production orders) in MRP3 view in material master and create a sales order for this material.

The sales order will have a tab Production order(similar to PR creation from third party order)

Reg,

Deepak,.

Edited by: deepak k b on Nov 20, 2008 10:29 AM

former_member225662
Active Contributor
0 Kudos

Hi,

You can do this through Img-MM-CBP-Procurment proposals-Define order profile.

Regards

KK

kunal_ingale
Active Contributor
0 Kudos

hi

use code CO01

regards

kunal