Flexible Planning - Multuple Material transfer to Demand Management.

May 11 at 02:03 PM

26

avatar image
Former Member

Hi Team,

We are using flexible planning and want to transfer the Multiple Material to Demand Mgm by following below Method. In MC8T- Activity -UEBERGABE , Field - PRODU maintain and MC8S (Transfer Profile) is maintain with below details.

Strategy -6
Table - SXXX
Field name - PRODU
Reqmts type - LSF
Version - 00 ( tried with IS as well)

Active - check mark.

1) MC8D 2) MC8E 3) MC8G

however we are not getting results in MD63 and we are running below message after Batch job run.MA640: No data maintained for material XXX plant XXXX in transfer period. If we run MC90, only single material get transfer successfully. Please help to know the process to send multiple material to Demand Management.

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

1 Answer

Best Answer
avatar image
Former Member May 18 at 04:03 AM
0

Hi Team,

Strategy - 9 should be there and its tested successfully. As I got the answer, closing this question.

Regards,

satish

Share
10 |10000 characters needed characters left characters exceeded