Hi all,
we run an XI 3.0 sp 21. we do high volume (we think..)
from sxmb_moni processing statistics :
- XML Messages/Day 9.704
- Minimum 1
- Maximum 295.940
- Today 172.008
retention is 3 days.
the switch procedure takes from 01:00 to 17:00 for the copy of about 750000 entries.
this job runs each day.
Questions :
is this duration normal ?
do we need some index or suchlike ?
if you run a comparable load, what are your runtimes ?
I would very much like my switch procedure to finish before start of business...
Regards,
Ronald van Aalst