Hi Gurus,
We have a problem with planned cost for the BOM in process order
We are not getting planned price for in-put materials, where as we are getting actual cost for the in-put materials
We have maintained price in material master.
Split valuation also maintained for the materials.
How to get the planned price for those in-puts.
please any body suggest me in this.
waiting for the reply
regards,
anand.M
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear anand,
please check in the material master product costing view genaral data with qty structure is ticked?
sree
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
HI
1.You should have completed standard costing
2.there sholud be Plan costing varient for the the order type . check wether the variant is there or not in control tab in order header.
3.check the settings OPL1 and these are assigned in OPL8 controlling tab
-ashok
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
107 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.