Hi Gurus,

We have a problem with planned cost for the BOM in process order

We are not getting planned price for in-put materials, where as we are getting actual cost for the in-put materials

We have maintained price in material master.

Split valuation also maintained for the materials.

How to get the planned price for those in-puts.

please any body suggest me in this.

waiting for the reply

regards,

anand.M

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

Please find the link

Thanks and regards

E.Rambabu

Answers (2)

Answers (2)

Former Member
0 Kudos

Dear anand,

please check in the material master product costing view genaral data with qty structure is ticked?

sree

Former Member
0 Kudos

HI

1.You should have completed standard costing

2.there sholud be Plan costing varient for the the order type . check wether the variant is there or not in control tab in order header.

3.check the settings OPL1 and these are assigned in OPL8 controlling tab

-ashok