on 11-19-2008 6:37 AM
Hi Gurus
I need Project settlement to be run automatically on a daily basis as a background job. I used CJ8G gave the background processing indicator and gave the operation mode as 'NIGHT' in the job indicator pop-up yesterday but nothing happened when I checked today. I did some more trials and it works when I assign immediate start in the job indicator but I can't seem to throw any light on how to run in daily automatically.
Best Regards
Renjith
Edited by: Renjith Yesudasan on Nov 19, 2008 7:37 AM
Fixed ! The problem was with the SAP time. It was different from the system time.