running mrp for a particular group of amterials

deepu_p2
Active Participant
0 Kudos

How do we run mrp for a particular group of materials.not for the whole plant.like running mrp to mrp group.

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

You also have three other choices:

1. MPS vs MRP for splitting into two sets of materials, e.g. daily MPS for manufactured material and weekly MRP for purchased material.

2. Running Single Item, Multi-level MPS (MD41) or MRP (MD02) for a product group

3. Develop an ABAP using your selection criteria (based on view MA61V?) that makes calls to FUNCTION BAPI_MATERIAL_PLANNING.

Regards

Alex Dixon

Answers (2)

Answers (2)

Former Member
0 Kudos

you can run MRP for materials based on there MRP controller with some exit,

so and as provided to you the link you can achive that easily

Pravin