on 11-18-2008 2:22 PM
How do we run mrp for a particular group of materials.not for the whole plant.like running mrp to mrp group.
Hi,
You also have three other choices:
1. MPS vs MRP for splitting into two sets of materials, e.g. daily MPS for manufactured material and weekly MRP for purchased material.
2. Running Single Item, Multi-level MPS (MD41) or MRP (MD02) for a product group
3. Develop an ABAP using your selection criteria (based on view MA61V?) that makes calls to FUNCTION BAPI_MATERIAL_PLANNING.
Regards
Alex Dixon
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
you can run MRP for materials based on there MRP controller with some exit,
so and as provided to you the link you can achive that easily
Pravin
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
103 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.