Skip to Content
0
Former Member
Nov 18, 2008 at 12:32 PM

CN60 - Change documents to trace the changes in project

562 Views

In order to trace the changes made in projects, we have activated the "Change Documents" in project profile customizing. On running the transaction CN60, the output is failed to display any changes and we are getting the message " No objects were selected using the criteria entered". However, if you open the project using transaction CJ20N and check the administration tab of the WBS, it shows the object was changed and the date on which it was last changed. We are talking about the situation after activation the "Change Documents" in project profile. May we request you to explain the failure of CN60 to display the changes in project.

Issue : 2 :

In case of collective run i.e. some transaction like create settlement run, collective run of RA, there may be some changes in project like creation of settlement rule, overwriting default RA key by RA key

defined in settlement strategy etc. How to trace or identify the changes occurred during such collective run?

Thanks and best regards

Bharat Parikh