Dear Pm experts,
When i schedule maintenance plan (counter base) then system generate more than one order, even counter reading is zero. Lots of orders are generating when counters are not updated. How to resolve this problem.
I have used
call horizon 100 %
plan for 365 days
Start of cycle : current date ( 01.11.2008 )
cycle period : 2500 strokes or (Numbers)
I have maintain my equipment no. in the production routing.Strokes or numbers are updated from the production order of PP module (As 100 nos. production order confirm then strokes are updated against that equipment counter.)