operation splitting

Hi,

I have created individual capacities say for example w1 and w2 in work centre wrc1.in routing I have mentioned required splitting and given 2 as splits.in routing work centre wrc1 is assigned to operation.

I want to dispatch operation quantity 10 into these two work centres w1 and w2 , 5 quantites each so that both the operations can start at thje same time and finish quickly.

how to do this capacity levelling?In CM25 i can see work centre wrc1 but not its individual capacities i.e w1 and w2?

please reply.

Regards.

Add a comment
10|10000 characters needed characters exceeded

Related questions

2 Answers

  • Best Answer
    author's profile photo Former Member
    Former Member
    Posted on Nov 18, 2008 at 03:21 AM

    Hi,

    In CM21, you can dispatch the operations only based on the work center.

    To dispatch for individual capacity, use CM27 in which you can perform Capacity Levellinty with splits

    Hope this helps for your requirement.

    -Thaila Shree

    Add a comment
    10|10000 characters needed characters exceeded

    • Former Member

      Hi,

      Is it possible to split the planned orders into individual capacity in CM27?

      i can able to split the production orders in CM27, we are not getting planned orders in CM27, is it possible or right way to do it?

  • Posted on Nov 17, 2008 at 05:04 AM

    Dear,

    Capacity leveling transaction "CM21" you would be able to dispatch individual operation quantities to the individual machines.

    For operation split you have to createM/c with 2 Indiviudal capacities and have also defined the Individual Capacities by name in the Capacity header CR02. Also in the capacity header you should have activated "Relevant for Finite scheduling".

    In the Scheduling parameters for the order type/Plant you should have activated check box for "Generate Capacity requirements" in transaction OPU3.

    You can only "Dispatch" the same in CM27 by assigning in "Cap. reqmt assignment" in production order. The indicator "D" is set only after the split is dispatched.

    Hope clear to you.

    Regards,

    R.Brahmankar

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.