Hi,

we have to Upgrade solution manager from 3.2 to 7.0 in an Upgarde project .i have 3 questions

1) how much time is required for the solution manger Upgrade(in days)

2) when do we Upgrade solution manger,will we do it before the Dev Upgrade or can we do the Upgrade of solution manager any time during the technical Upgrade

3) we use Solution mnager to generate the Upgarde key ,Can we do it with any version of Solution Manager?

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • avatar image
    Former Member
    Nov 25, 2008 at 10:16 AM

    Hello,

    to 1) The technical steps of an SolMan upgrade can be performed in less than 2 days, including backups, preparation phase, upgrade phases and some post activities. The run time depends on your system size and hardware, of course.

    to 2) I dont' understand the question. Is the DEV system you are talking about another SolMan System? Please specifiy.

    to 3) Yes, any version can do it.

    Best Regards,

    Holger Slomka

    Add comment
    10|10000 characters needed characters exceeded

    • Former Member Markus Doehr

      Hi Markus,

      We did the Unicode migration separately, so we could reduce the downtime. But of course we also had a huge amount of SAP notes to implement. I was just speaking about the technical runtime, the overall project took much longer, including preparation, DEV system upgrade, testing, ...

      Because we already used CHaRM since end of 2005, we also had no choice to install a fresh system, but I would also prefer. Also we could not implement the new BC Sets for Charm, so we had to check the differences ...

      Best Regards,

      Holger

  • Nov 25, 2008 at 12:15 PM

    >

    > we have to Upgrade solution manager from 3.2 to 7.0 in an Upgarde project .i have 3 questions

    > 3) we use Solution mnager to generate the Upgarde key ,Can we do it with any version of Solution Manager?

    Hi Swaroop,

    Are you using your SAP Solution Manager system to generate Installation/Upgrade Keys, only?

    If yes, my suggestion is the following:

    - setup a new SolMan 7.0 and don't upgrade your existing SolMan 3.2. This saves time and money.

    - shut down the SolMan 3.2, once you have finished the configuration of SolMan 7.0 and the system is up and running.

    Best regards,