CM25 capacity leveling on same work with diffrent materail but same time

Dear All,

We are producing two different materials (with two different production order) on same WorkCentre.

Is it possible to get to schedule two production orders at the same time on same work centre with CM25? We are using a CM25 transaction for capacity levelling.

Could you please help how to handle this in CM25? or I need to add some additional data in routing or work centre.

Here I am attaching a screenshot of CM25. Currently both the material production plan with finite scheduling.

If you need further information then please let me know.

Thank you in advance.

Regards,

Maulik

cm25.png (157.0 kB)
Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • May 09, 2018 at 01:38 PM

    Hello

    In the work center capacity there is a flag called "can be used by several operations". If you check this flag, you will be able to dispatch several operations at the same time to this work center.

    Otherwise, you can use define individual capacities in the work center and use a profile in CM25 that allows you to see individual capacities.

    Regards,

    Caetano

    Add comment
    10|10000 characters needed characters exceeded

  • Mar 10 at 08:52 PM

    Hi Maulik,

    As Caetano rightly mentioned, it is suggested to create individual capacity in the work center, then use a custom profile (or even standard profile SAPSFCG005) in CM25.

    If there are more than two splits in same work center, then you can use "Split/Allocate" function, or "Splitting" option under order->operation to schedule same order in multiple lines of single WC.

    Thanks

    Prem