Former Member
Nov 13, 2008 at 02:35 PM

Capacity Planning CM01 Question?

36 Views

We have a production order schedule for a workcenter over 3 Days.

The workcenter capacity is 15.74 HR

When i run CM01 without any Qty confirmed.

Day 1 has Requirements as 14.24 HR

Day 2 has 15.7HR

Day 3 has 15.7 HR

After i did a confirmation for Qty 1000.

Day 1 has 13.28 HR

Day 2 has 14.67 HR

Day 3 has 14.67 HR

My questions is why would capacities for Day 2 and Day 3 reduce. All the hours should have been consumed from Day 1 ?