We have a production order schedule for a workcenter over 3 Days.
The workcenter capacity is 15.74 HR
When i run CM01 without any Qty confirmed.
Day 1 has Requirements as 14.24 HR
Day 2 has 15.7HR
Day 3 has 15.7 HR
After i did a confirmation for Qty 1000.
Day 1 has 13.28 HR
Day 2 has 14.67 HR
Day 3 has 14.67 HR
My questions is why would capacities for Day 2 and Day 3 reduce. All the hours should have been consumed from Day 1 ?