Hi,
Supposr I have PRODUCTION ORDER for material A for 10 pc in which operation are,
10-tURNING
20-Plating
30-Deliver to Store
Now I want to perform operation 10 on two workcenter w1 and w2 each for 5 pc of A.
Now how I can do this in SAP as we can not confirm operation 10 two times for two workcenter.So I want way through which I can confirm 5 PC of A on workcenter W1 and 5pc of A on workcenter W2 for operation 10.Total for INPUT FROM OPERATION 10 TO operation 20 is 10 PC.