author's profile photo Former Member
Former Member

Sender activity type in time sheet

Hi all,

while entering time data in time sheet against network & activity, selected from the work list, the system issues an error msg : assign activity type for the cost center XXXX.

We do not want to capture or allocate any cost to PS.

Question is, how can we skill entering activity type in the time sheet for entering time against each activity.

Pls help

Thanks,

Chandru

Add a comment
10|10000 characters needed characters exceeded

Assigned Tags

Related questions

2 Answers

  • author's profile photo Former Member
    Former Member
    Posted on Nov 13, 2008 at 11:55 AM

    Hi

    You will have to maintain it in KP26 with valid periods. Do not put any rate in it if you do not want the cost.

    Regards

    Add a comment
    10|10000 characters needed characters exceeded

    • As Hemanth told that is one way..

      But if you don't wanted to activity type to be appear in system than keep the same as hidden /display filed using Influencing filed of Data Entry profile, based on requirement.

      PS -CATS integration is defined based on two main point your activity type & Cost Center ( Normally you use CATS for time / Cost booking it will get recorded in Cost center & activity type )

      Now the question is why you want PS CATS ?

      With Regards

      Nitin P.

  • author's profile photo Former Member
    Former Member
    Posted on Jan 09, 2010 at 11:54 AM

    Hi,

    For booking of time sheet through CATS, it requires mandatory fields.

    Cost center

    Activity type

    CO object(internal order, n/w or activity, WBS, SO, Cost center)

    For booking the time sheet through CATS:-

    - rates should be maintained in cost center w.r.t activity type.

    - personnel number with the responsible cost center.

    - data entry profile.

    Also whenever we are booking the time sheet, we are booking the hours against some of the activity performed in business such as project management, erection, commisioning etc. So that we can check the cost on the project related to various business activity.

    Thanks & regards,

    KK

    Add a comment
    10|10000 characters needed characters exceeded

    • Former Member Former Member

      Hi,

      my qusetion is, whats the purpose you are having to use CATS with PS integration.

      Is it only you want to monitor the hours spend on each activity by the resource?

      And you donot want to book any secondary cost to network /WBS Element.

      And how the actual cost is being booked.

      Please reply so that we can think to address the issue.

      Regards

      N.Raju

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.