Configurable material in scheduling agreement

former_member403242
Participant
0 Kudos

When I use DS scheduling agreement with LPN as item category with configurable material, I cannot input value for configuration. But if I use normal TAN instead of LPN, I can input value for configuration.

Why?

Does SAP do not allow configurable material in scheduling agreement or quantity contract?

Thanks in advance for any suggestion.

Accepted Solutions (0)

Answers (3)

Answers (3)

former_member403242
Participant
0 Kudos

Thanks for all replies.

The problem sovled by change requirement type.

former_member204513
Active Contributor
0 Kudos

Deat Amy,

Please check the item category settings related to configuration through VOV7 transaction.

Go to VOV7 transaction then select item category LPN then go in to the detain here you check the configuration related settings under Bill Of Material /Configuration tab.

If want you refer the standard Config.at Mat.Levl itemcategory TAC settings, same way you can do settings for your item category then try.

Note:- Not advaisable to change the standard one, so you copy the standard itemcategories do the changes,

I hope this will help you,

Regards,

Murali.

Edited by: Murali Mohan.Tallapaneni on Nov 13, 2008 5:20 AM

Former Member
0 Kudos

Hi,

Just check out which requirement class is getting triggered. (Eg. When u make normal sales order requirement class 011 - Delivery requirements gets triggered).

Then go to OVZG transaction and assign * Configuration allowed to the configuration tab.

Regards

Mahesh