Hi,

We would like to run SAP APO - Deployment heuristics (Fair share rule A) - at 3 levels

1) Plant to Regions

2) Regions to States

3) States to Dealers.

Once the deployment run is executed between plant to regions, the results are required to be modified before executing deployment between regions and state.

E.g. If plant has stock of 10 and there are two regions (R1 & R2 with demand of 10 each),

by fair share rule, system will create Deployment Con Rel of 5 from Plant to R1 and 5 from plant to R2.

But it is required that a central team will modify this result (5 & 5 ) as say 6 for R1 and 4 for R2 so that further deployment from R1 to states should deploy 6 quantities.

The Key figure (ATD receipts) is not editable in planning book. How can this be changed?

Accepted Solutions (0)

Answers (0)