Dear friends,

We are using the Sch.Agreement via ME31L.

After creates the Sched.Agreement we go there at pricing and input a freight condition.

But when We are receiving , no accrual are done and also at MIRO the conditions do not appear.

Does anyone know If Is possible to work with freight in Schedule agreements ?

PS.: we are using the same pricing of PO , RM0000.

best regards,

Ale

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

If you are using the std pricing and account determination is done than you will see the Delivery condition in the accounting document

when you post the invoice that time select the goods/service item + planned delivery cost

than only you can see

Former Member
0 Kudos

Dear friend ,

Yes we are using std pricing .

Thanks.