Project Progress Calculation

57 Views

Dear All,

I have query for project progress calculation.

As you know that we have std project progress reports( CNE1/ CNE5), In these reports , project progress are calculated monthwise because as per the prerequisite of CNE1 report, input parameter is period ( month, year). If client wants project progress report on a specific date e.g. 15.11.2008 then system gives the progress report , considering plan poc by the end of the month Nov i.e. 30.11.2008, not upto 15.11.2008.

If you faced such scenario, please share your experience.

Regards,

Ashok Sangal