Repetitive Mfg: Supply area in planned order

Former Member
0 Kudos

I am using Repetitive Mfg and have created a planned order for material FG1 which has component C1. I have created a Routing for FG1 with one operation with a Work center. I have assigned the supply area to this Work center. When I create a planned order for FG1 the supply area is not getting copied to the component screen of the planned order. Is there something I am missing here?

thanks

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

Don't know what other modules you are using - for example, if you are using WM then you might be missing a control cycle for the component / supply area.

Hope that helps

Alex Dixon