Hi All,

Business process being followed

1. Business upload PIR for whole year at once and planning is done on that i.e. Made to stock.

Business is using strategy 10 but they want PIR to be reduced on GR against process order.

Also, they want stock to be considered so they dont want stratergy 11.

I have asked earlier about combination of these two stratergies but I guess thats not possible(std). What will you folks suggest here?

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

1 Answer

Raghavendra Rao P V S May 07 at 07:50 AM
0

Hi

I dont think you can achieve without using an enhancement

Can you look at the BADI MD_CHANGE_MRP_DATA

The method "CHANGE_MDPSX_PLAF" can be changed for the planned order quantity

Regards

Raghavendra

Show 1 Share
10 |10000 characters needed characters left characters exceeded

Hello Sir,

Thank you for reverting back. I checked mentioned BADI and multiple threads/blogs based on it and understood that through this we can control planning and stock requirement list generated.

I dont have much experience with BADI implementation and will really appreciate if you can give me a little more help here. I want to understand it completely before moving to my ABAP person with requirements.