Efficient MRP stratergy for this business scenario

Hi All,

Business process being followed

1. Business upload PIR for whole year at once and planning is done on that i.e. Made to stock.

Business is using strategy 10 but they want PIR to be reduced on GR against process order.

Also, they want stock to be considered so they dont want stratergy 11.

I have asked earlier about combination of these two stratergies but I guess thats not possible(std). What will you folks suggest here?

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • May 07 at 07:50 AM

    Hi

    I dont think you can achieve without using an enhancement

    Can you look at the BADI MD_CHANGE_MRP_DATA

    The method "CHANGE_MDPSX_PLAF" can be changed for the planned order quantity

    Regards

    Raghavendra

    Add comment
    10|10000 characters needed characters exceeded

    • Hello Sir,

      Thank you for reverting back. I checked mentioned BADI and multiple threads/blogs based on it and understood that through this we can control planning and stock requirement list generated.

      I dont have much experience with BADI implementation and will really appreciate if you can give me a little more help here. I want to understand it completely before moving to my ABAP person with requirements.