on 05-07-2018 7:28 AM
Hi
Please see my query about the activity pricing.
We have created a PO on today with start date and end date after 3 months (i.e. in June 2018).
My doubt is : which activity price the Production order will consider while saving the cost estimate ? : is it the price on today (April 2018) or price that will be for June 2018 ?
Please guide.
Dear nikki saju,
For production order cost calculation, system uses Scheduled date for activity prices.
For your example if the Scheduled date is june 2018, system uses june 2018 activity prices.