Hi Experts,

Can you help me to map the following process:

Client has a machine (Excavator) which loads different trucks. For this we have to define a routing in such a way that the trucks loaded qty by the machine (Excavator) should comes as a combine GR qty for that machine (Excavator)

Operation 10 - Excavator (Work center) - 300 kg ---------- Total sum of following suboperation which is 300 kg should be my GR qty.

Sub-operation 10 - Truck 1(Work center)- 100 kg

Sub-Operation 20 - Truck 2(Work center)- 100 kg

Sub-Operation 30 - Truck 3(Work center)- 100 kg

In sub-operation system is not allowing me to confirm the qty. Yield field gets grey out.

Regards,

sun

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

1 Answer

Raghavendra Rao P V S May 07 at 07:11 AM
0

Hi

Why cant u have separate confirmations for each truck.Change the truck (enter the actual work center) during the confirmation

GR can be done using MIGO

Regards

Raghavendra