We are using APO system.

1. In UAT System - When I am creating production Order the Operation status is REL.

2. Immediate after saving production Order, the Operation status is set DSEX - Date set by external System.

3. Production Order getting change by RFC user. I am not able to understand what this RFC user doing. I can See production Order Changed by RFC user in administration TAB.

4. But for same material in Production System this is not happening. Need your help to understand what I have missed .

Here my requirement is that production order operation will not set with status DSEX as it is not happing in Production System and in both the system material is with MRP type X0.

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

2 Answers

Caetano Almeida
May 05 at 08:05 PM
0

Hello

This status is set when the operation is scheduled in APO. You should check if the work center is part of an active integration model at APO and deactivate it, if this kind of operation should not be planned in APO.

Regards,

Caetano

Show 1 Share
10 |10000 characters needed characters left characters exceeded
Former Member

Hi Caetano,

Thanks for your reply.

Yes, This work center is part of integration model.

But Production order with Operation Status DSEX is created in Quality system and not on Production System.

Our APO consultant has check all data in QA and production and it is look like same.

0
avatar image
Former Member May 08 at 03:26 PM
0

Hi Team,

can please share your thought.