Scenario is like this

Stock transfer without biling, after creating sto we create Goods Issue till that time value is updated in system, after that when we are posting GR value is not updating and it is taking zero value.

When we check in PO (Purchase Order History) it is updated with zero value.

Regards

Shrikant Kamat.

Add a comment
10|10000 characters needed characters exceeded

Related questions

4 Answers

  • Best Answer
    author's profile photo Former Member
    Former Member
    Posted on Nov 11, 2008 at 08:00 AM

    Hi,

    Value won't be updated at the time of GR if you do intra-company STO.(101 mvt typ)

    It will only happen when you PGI in the Issuing plant.(641 mvt type)

    Reg,

    deepak

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Nov 11, 2008 at 08:34 AM

    Hi Deepak

    then how the receiving plant will extract the amount while dispatching the material which has came against the sto.

    Add a comment
    10|10000 characters needed characters exceeded

    • Former Member

      Hi,

      It will be valuated based on the Issuing plant price,when PGI happens.

      It depends on the price control indicator and the price based on which material will be issued from the recieving plant.

      Reg,

      Deepak.

  • author's profile photo Former Member
    Former Member
    Posted on Nov 11, 2008 at 08:37 AM

    Hi,

    Check for this material type whether Value Update is checked or not in OMS2 transaction.

    Regards,

    Venkat

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Nov 11, 2008 at 08:57 AM

    Dear Venkat

    Value updation is done in OMS2, any other option is there.

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.