Activity missing in Workforce planning:project view

Dear experts,

I an caught up with the following problem:

1) I created a project with WBS and activities.

2) Created relationship between activities.

3) Created project team

When I try to perform workforce planning (project view) using transaction CMP2, some of the activities are missing in the list.

Please let me why this happens and also how to include the missing activities.

Thanks and regards

Add a comment
10|10000 characters needed characters exceeded

Assigned Tags

Related questions

4 Answers

  • author's profile photo Former Member
    Former Member
    Posted on Nov 11, 2008 at 09:57 AM

    Hi John,

    Please try out the following link as it may help you :

    http://help.sap.com/erp2005_ehp_03/helpdata/EN/4c/2279eb46e611d189470000e829fbbd/frameset.htm

    Thanks,

    Dhruv Kumar Malhotra

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Nov 11, 2008 at 11:12 AM

    Hi

    Please check following prequisites-

    1.HR mini-master record (infotypes 0001and 0002).

    2.Assigned work centers to the internally processed activities.

    3.Entered Formulas in the work center to determine capacity requirements.

    4.Scheduled the activities to generate capacity requirements.

    5.Assigned only one labor capacity to a work center. (that is catagory 002)

    6."Determine Cap. Check" indicator is ticked in the network header.

    Regards

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Nov 11, 2008 at 11:31 AM

    The problem would be workcenters. Check whether you have assigned it in the activity. Along with workcenter provide allocated hours and a distribution rule. Check and confirm.

    Add a comment
    10|10000 characters needed characters exceeded

  • Posted on Nov 11, 2008 at 01:25 PM

    open project in Project planning board

    go to Edit -> function -> activate capacities

    then Go to -> capacity levelling -> workforce planning

    if this does not work then check the configuration/ details as explained by Hemant

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.