Skip to Content
0
Former Member
Nov 11, 2008 at 04:30 AM

Result Analysis Valuation Method 3

47 Views

Hi PS Experts, The building block document on Profit Realization 'I58_BB_ConfigGuide_EN_DE' says that as per IAS 11 and 18, we need to configure Result Analysis Valuation Method 3 only which is cost based. Is it right and whether you are all having this valuation method in your SAP system where IFRS standards are applicable. Then, in addition to this cost based Revenue Recognition through this valuation method 3, we would like to input realistic POC(Engineer's certificate) into the system. Whether it is possible and if so, how and what other valuation method we need to use with or with changes to a particular valuation method. Appreciate your valuable inputs on this. Regards!