Dear experts,

Please find the below scenario and guide further:

There are two plants (A and B).
A is into sales order capturing whereas B is into to production activities.

Below are the expected activities between these plants:

Plant A:
SO (12345) (with auto PR) -> PO (wrt PR). And this PO should be to Plant B.

Plant B:
1. SO Transfer (12345) from Plant A to Plant B (but material differs between these plants for the same item).
2. WBS BOM (using material code of Plant B)
3. BOM updation
4. MRP is run to create PR -> PO -> GRN from Vendor.
5. Outbound delivery to Plant A

Plant A:
GRN (wrt PO from Plant B)
Outbound delivery to Customer.