Dear Guru's,

Users intend to use Kanban system. We have prepared case where material moves from Storage location to production supply are on shop floor. But how to move from supply area to work center i.e. goods issue to production order. We use discrete manufacturing i.e. production order.

Regards,

SAP CONS

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • May 07 at 10:12 AM

    Hi
    If I understood correctly, you are trying to do the Goods issue from the Supply Area.
    If tis is the Case, you can assign the Supply Area, to the Work Center. Then you need not to do the goods issue again from Supply area to the Work Center, as a Separate step. Please assign the Supply area, in the Work Center Basic data tab, as shown below, then the system will take care of the Goods issue automatically.
    Hope, this is clear. Kindly let me know, for any further assistance required. Thanks & Regards : Raja S Reddy

    Add comment
    10|10000 characters needed characters exceeded

  • May 12 at 12:53 AM

    Hi

    Thanks for the kind feedback.
    Just based on the screen shots, it seems, you are trying to perform the stock Transfer using the KANBAN.

    1). Is it between the IM Storage Location ?, Is it so, Please take a look of the attached screen how, it looks like

    Please take a look of this link, which describes the sequence of the steps to be followed for the KANBAN Process, for the Inhouse, Replenishment, for the Production : https://blogs.sap.com/2018/04/11/kanban-process-in-s4-hana-1709/

    If still facing the problem, please describe the sequence of steps, that you are following & at which point, it is not working
    Thanks for the kind feedback . Best Regards : Raja