on 11-09-2008 10:27 AM
hi,
where i can add annual estimation of the counter,in a single cycle maintenance planning so that according to that annual estimation system will generate order through Maintenance Plan?
With best regards,
well you have to give the annual estimate in measuring point (counter) Transcation IK11, here you can maintain the annual estimate on basises of which u can trigger or genrate maintenance call objects (notifications and order )
after that in single cycle plan you give the cycle length and in the maintenance scheduling parameter TAB (2nd Tab at header)maintain scheduling period like 365 days and then scheduale the maintenance plan ... you will see different dates which will be scheduled according to annual esitmate ...
Regards
Iftikhar
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thanks experts,
my problem is solved
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi
Annual Estimation of a counter can be maintained while creating Measuring Counters using Tcode ip41.
Regards
BK
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
sorry i put the wrong transaction that was for Measuring document
any ways transaction for Measuring counter is IK01
Go to Transaction IK01 --->Measuring point Object ENTER or SELECT (IEQ)
-
>Equipment Number (Enter Equipment Number )
-
> Equipment Category
-
> Then there will indicator of Counter check that indicator
Press enter then at bottom of transaction you will find Annual estimate.
I sure this time you will find it.
Regards
Iftikhar