Skip to Content
0

Random error "Master cannot read return value from subprocess" while executing planning sequence

May 04 at 10:56 AM

51

avatar image
Former Member

Hi Experts,

I am getting the below error when running a planning sequence from process chains.

"Master cannot read return value from subprocess". We have enabled the option "process in packages" with manual adjust. There are only 600 values for the dimension with which packaging is enabled with 30 packages and max of 21 values each.

The step fails randomly only on few days, and it gets completed successfully if we run it manually from RSPLAN with the same variants.

Please help ? Thanks in advance.

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

1 Answer

Andras Margitics
May 07 at 09:04 AM
0

Hi Ramesh,

Do you have any additional dump in ST22?

That should help.

Best regards, Andras

Show 2 Share
10 |10000 characters needed characters left characters exceeded
Former Member

Hi Andras,

We have the attached dump created in ST22.

st22dump.txt

Thanks


st22dump.txt (137.1 kB)
0

Hi,

Please check and implement these notes:

2031406 and 2095155


Best regards, Andras

0