Dear friends

This the scenario with respect to product cost by sale order settlement profile. When I am settling the process order, which is created with reference to Sale order, system throwing an error "Define a settlement cost element for receiver type SDI".

When I see the explanation given by system, the following message displayed :

"Diagnosis

In allocation structure Z1 (controlling area RI01), you did not define which cost element should be used when settling costs/revenues of the sender. Nor did you define receiver type SDI.

Procedure

Assign a different allocation structure to the settlement sender (-> Master data -> Settlement rule -> Goto -> Settlement parameters), or maintain allocation structure Z1.""

For this I have defined one Secondary cost element and assigned to Allocation Structure under Settlement cost elements.

Still I am getting the error. What could be the reason?

Please do the needful.