Greetings...

i have capacity of work center which start from morning 8 a.m to 17.30 p.m.(One Shift) wich i defined in work center. Now I cretaed production order wich carried in above work center. In production order, Go ->Grafics ->Gant Chart.

In gant chart with time unit as HOUR..i am getting that its showing operations is scheduled on after & before defined time ( 8.. a.m. to 17.30 p.m). Also sunday is holiday as per factory calender,..operation schduled on sunday...

Hows It ?? Some of operation start and end at sunday ??? Its giving me some confusing picture ???

How to clear it ?????